The Town of Millbury has received FY 2021 Community Development Block Grant funds from the Massachusetts Executive Office of Housing and Livable Communities to make improvements to public works infrastructure on Pearl Street, including its intersection with Providence Street. Upgrades will be made to water and sewer mains, stormwater drainage, sidewalks and pavement, starting in August of 2023. During project work, there will be some disruptions to traffic and parking, and water and sewer service may be unavailable for brief periods during certain construction activities and testing. Access to some parking spaces at the Millbury Housing Authority’s Linden Apartments may be limited at times. Pearl Street residents are encouraged to consider parking on Maple Street temporarily. Updates to the project work or schedule will be posted here in the event of substantive changes.
Anticipated Project Schedule
This is an anticipated schedule. The schedule may change based on availability of materials, weather conditions, unexpected site conditions, or other factors.
- Ricciardi Brothers, Inc. was hired as the Town of Millbury’s general contractor
- Construction mobilization in mid August
- Water, drainage and sewer utility work in August and September
- Sidewalk, berm and driveway repair work in September and October
- Roadway binder (base) paving in late October
Final roadway paving utilizing other grant funds is expected in the late fall of 2023 or in the spring of 2024.